Offshore Wind Power Project in the Southern Shandong Peninsula


发布时间:

2022-09-05

On December 5, 2021, our "Southern Shandong Peninsula Phase 3 & 4 Offshore Wind Power Project" – with 88 wind turbines and 37 monopile foundations installed – was successfully completed ahead of the 2021 offshore wind power subsidy withdrawal & grid-parity deadline (December 31). Mobilizing 9 teams (350+ staff) across 3 wind turbine installation vessels ("Dejian", "Defu 3", "Huadian CIMC 02"), 3 piling vessels ("Zhifu Island", "Defu 15001", "Huadian CIMC 01") and 3 onshore terminals (Sheyang, Rushan, Haiyang), the 222-day project set a record of 12 turbines installed in 29 days!